Construction Update: February 5, 2010
Picture of fully topped out Solera building. Plastic tarp currently covers building exterior to protect scaffold plates from snow and to retain building heat. Exterior framing is now complete on all floors and interior framing is complete up to the 10th floor. Windows are installed up to the 8th floor.
Picture of south building façade of masonry base with residential floors above.
Tyvek is currently being installed to function as building’s vapor barrier. Installation of the permanent building elevators has started; an 8 week process.
Construction of Solera’s structural steel architectural element that runs up the corner of the façade is currently underway.